PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Scope Management
Mary is a new project manager in your company. She came to talk to you and get some advice on creating a work breakdown structure. You discussed the process with her and she is asking what software to use to create the WBS and what she should do with it when it's completed. You respond that the picture is not the most valuable result of creating a WBS. The most valuable result of a WBS is: