Stakeholder Management
Your most recent project is to oversee the installation of charging stations for electric vehicles in rural areas. Currently you have been trying to identify internal and external stakeholders who might be interested in the project and can positively or negatively impact the project. During the stakeholder identification, you realize that stakeholder identification: