Stakeholder Management
You are the project manager of a software deployment project for your company. This project will upgrade the operating systems for company's employees. Many of the employees are in favor of this change, others are not. As part of your plan, you complete an analysis of the stakeholders. In this analysis, you and the project team have also learned that the functional managers are not in favor of the change of the operating system for their employees’ laptops. How would you classify these stakeholders?