Stakeholder Management
The project manager is reviewing the stakeholder management plan and communications management plan. He is focused on meeting and exceeding stakeholders' expectations by communicating with them, resolving their issues and improving project performance by implementing their change requests. Which stakeholder management process is the project manager in?