PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
The company where you are working as the project manager is using an agile approach to project management. The development team is rating the difficulty of completing the requirements in the current sprint. The term that describes rating of the requirements to determine how many requirements can be completed in a sprint is: