PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Quality Management
The project manager has been assigned to oversee the software development project. The project manager has to determine things such as what level of quality efforts are appropriate for the project, what equipment or technology should be purchased and whether it would be best to outsource the testing part of the work. He has identified the point where the revenue from improving quality equals the incremental cost to achieve that quality. Which analysis has been performed by the project manager?