PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
In the middle of project planning, the project manager learned that he was given inaccurate data regarding new regulations affecting the required end date of the project. He might need to make some adjustments. Nonetheless, the project manager believes he will still be able to manage the project to complete it before the regulations take effect. He confirms it by analyzing the sequence of activities with the least amount of scheduling flexibility. The project manager used the following technique: