You have been assigned to manage a new human resource application for a large organization. They want it to help with searching for new employees and hiring them. Your team will be working on requirements affecting the needs of some of the stakeholders through the project. Other stakeholders' requirements will come into play during the end of the project. The stakeholders have the most impact on a project: