PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
The project manager is in the Sequence Activities process of the project to combine two separate visual effect applications into one. His company wants to create an application that could be used worldwide. It must have all possible functionalities and be available in most common languages. The project manager is currently identifying and documenting relationships among defined activities and arranging them in order in which they must be performed. The project manager will be using the precedence diagramming method (PDM). Which of the following statements about precedence diagramming method is FALSE?