Resource Management
You are managing a project to combine video clips for a commercial video for your client. There are many specific requirements as to the color grading and audio. The most talented employees from your company are in your team since this project is major and is expected to bring the most profit this and next year. Three weeks ago during the morning meeting, you were informed by one of the team members that a complex problem arose. This problem could have an extremely negative impact on the project. You decided to analyze the problem right away using a fishbone diagram to define the cause of the problem. Then you identified a solution and implemented this solution. Today you received an email from the same team member who informed you that the same problem resurfaced. Which of the following things you most likely forgot to do?