You are the project manager for your organization and you are training a few junior project managers. You’re currently reviewing the inputs for Monitoring stakeholder engagement with your project team. The team members are confused about some of the inputs needed for controlling stakeholder engagement. One of the inputs to Monitoring stakeholder engagement is the issue log. How does the issue log help you prepare to control stakeholder engagement?