Procurement Management
You are managing a project which followed a strict software engineering process. A lot of attention to detail has been given while specifying the requirements. An interim project deliverable has been delivered to the buyer by one of your team members. You are surprised to find out that the buyer refuses the deliverable, saying that it doesn't meet the requirement on page 135 of the technical specifications. Of course, you review the document and realize that the buyer is right. The best thing for you to do is: