Cost Management
Which of the following statements is FALSE about cost baseline?
Cost baseline is usually displayed in the form of S-curve.
Cost baseline is a time-phased budget used to monitor, measure and control cost performance during the project.
Cost baseline aggregates the estimated costs of project activities to work packages, then to control accounts and finally, to the project.
Cost baseline assigns cost estimates for expected future period operating costs.