What is the best description of the difference between the Perform Integrated Change Control process and the Control Scope process?
Perform Integrated Change Control focuses on making changes to integration, while Control Scope focuses on making changes to the product scope.
Perform Integrated Change Control focuses on making changes to integration, while Control Scope focuses on controlling the scope of the project.
Perform Integrated Change Control focuses on determining the impact of a change to scope, time, cost, quality, risk, resources and customer satisfaction, while Control Scope focuses on making changes to the product scope.
Perform Integrated Change Control focuses on determining the impact of a change of scope on time, cost, quality, risk, resources and customer satisfaction, while Control Scope focuses on controlling the scope of the project.