lock iconProject Management Framework

You have been assigned a complex project to implement a new wireless media streaming device. Due to complexity of the project you need a few highly skilled technical resources with very specialized expertise and domain knowledge. You obtain these resources from the organization resource pool and different departments, specifying the duration and bandwidth for which they will be required. You also commit to release these resources to respective departments once your needs are fulfilled. In which kind of organizational structure are you working?