Project Management Responsibility
The project manager who was managing the highway construction project has resigned for personal reasons and you have been assigned to take on his project. While reviewing the deliverables and their status, you realize that some deliverables that were reported as completed are still in development. Also, you understand that the project is behind schedule and over budget, while the management is under the impression that the project is on track. What should you do in this situation?