PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconIntegration Management

In the middle of the project, the project manager has been told by the scheduler that the project control limits are secure. At the same time, one of the team members started complaining, that the manager of the accounting department won't help him until the activity's float is in jeopardy. The project manager notices that he has 5 voice messages left from a minor stakeholder and 10 emails from team members. Before he is about to get to those messages and emails, a team member walks in and says that a corrective action was implemented by a team member from the project management office, but was not documented. What should the project manager do?