lock iconSchedule Management

Your project is to create a network for a few affiliated companies. You have just finished design activities with your project team. Now, you ordered a few computers to set up the development environment and your team has to wait for a week before they can start the development work, as it will take a week for the vendor to deliver the computers. This week waiting time can be defined as: