PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
Your project is to create a network for a few affiliated companies. You have just finished design activities with your project team. Now, you ordered a few computers to set up the development environment and your team has to wait for a week before they can start the development work, as it will take a week for the vendor to deliver the computers. This week waiting time can be defined as: