Integration Management
You are the project manager for a logistics company operating in the USA. Your company has just introduced its services to Canadian market. You've been assigned to a critical project which will take three years. You are reporting on project elements such as deliverable status, schedule progress, costs incurred etc. Which of the following inputs of the Monitor and Control Project Work does this describe?