Cost Management
The cost baseline is displayed as an S-curve because of the way project spending occurs. This S-curve:
Indicates that the cost starts of low, accelerates throughout the later phases of the project and gradually slows down during the closing.
Indicates that projects run in a cycle.
Indicates that the bulk of the project cost is spent during the initiating and the closing phases.
Indicates that the project cost is directly proportional to the size of the project.