This app works best with JavaScript enabled.
PRACTICE
Home
Blog
Vocabulary
Sign In
Sign Up
Home
Blog
Vocabulary
Sign In
Sign Up
PMP Exam Simulator
Duration
3h 50m 0s
Questions
Start
Accelerate Mock Exam
Display correct answer
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
Choose the correct statement:
The network diagram will change every time the end date changes.
A project can never have negative float.
There can be only one critical path.
The critical path helps prove how long the project will take.
Next