PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Cost Management
You are managing a project to install shower cabins in 500 hotel rooms. You will need the same amount of materials for each room, as all the rooms will be identical. Your project team has completed the first three hotel rooms that took an average of two hours each to complete. You calculate the time to install the tile in each hotel room at two hours. The cost for the labor for your new project team is calculated at $300 per room. Your project sponsor disagrees with your labor estimate because: