PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
You are the project manager for a new training program of a large fitness center. This program will require each of the employees of the center to attend a half-day class and complete an assessment exam. You will be completing the training at the client's facility and will need a trainer for the duration of the training, which is three months. This is an example of: