Cost Management
The quality efforts on the project have gone through changes. Also, a few processes have undergone considerable change. The customer is satisfied with the work. However, he just found out that a competitive company is working to create a similar product. The team has been requested to analyze and create some options for the customer. Value analysis is performed to: