PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

The team has completed the project and delivered it to the customer. However, the customer notified them that a few deliverables are not acceptable because they don't meet the requirements specified early in the project. The project manager and the team go through the requirements documentation and agree that the product deliverables meet the customer's requirements as they understand them. The project manager seeks the advice of the project management office (PMO) to help determine what went wrong. After some review PMO sees that the Validate Scope process was not performed appropriately by the project manager. The key output of the Validate Scope process is: