PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Stakeholder Management
You are the project manager of a large software deployment project for your company. This project will replace the operating systems for the company's employees. Many of the employees are in favor of this change, others are not. As part of your plan, you complete an analysis of the stakeholders. In this analysis, you and the project team have discovered that some of the project stakeholders didn’t know about the change in the company’s approved computer operating system. How would you classify these stakeholders?