Stakeholder Management
The project manager is in the Monitor Stakeholder Engagement process. He is evaluating and monitoring overall stakeholder relationship and ensuring stakeholders' appropriate engagement in the project by adjusting plans and strategies. Which of the following is an important input to the Monitor Stakeholder Engagement process?