Scope Management
The project manager is in the Collect Requirements process. Which statement is FALSE about the Collect Requirements process?
The key outputs in the Collect Requirements process are requirements documentation and requirements traceability matrix.
The Collect Requirements process describes project deliverables and work required to create them in detail as well as deliverables description, product acceptance criteria, requirements assumptions and constraints and exclusions from requirements.
Interpersonal and team skills and data representations are used as tools and techniques in the Collect Requirements process.
The inputs in the Collect Requirements process are the scope management plan and requirements management plan.