PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

The project manager is working on a skyscraper construction project. He is currently in the Control Scope process. Which of the following statements is FALSE about the Control Scope process?