PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Scope Management
Your project on a new application is near completion. All the issues in the issue log have been resolved except one, which will be fixed in the next version of the application. You have released some team members, so they they could start working on new project as the management requested. The project team performed quality control inspections and met quality requirements for all of the items except one. You requested the product verification from the client but the client said they want a major change to the scope. What should you do in this situation?