PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconScope Management

Prior to creating the project charter, the project manager held a few meetings with the sponsor and stakeholders. In one of the meetings, the sponsor specifically denied funding for one specific item. Two stakeholders requested the project manager add work for the item which was denied by the sponsor. What should the project manager do in this situation?