Scope Management
The project manager overseeing a project to implement new software for an accounting firm requested his team to decompose project deliverables and the project work into smaller components to develop a WBS and WBS dictionary. The project team finalized the WBS by establishing control or cost accounts and unique identifiers for the lower-level components of the WBS called work packages. This WBS provides a structure for hierarchical summation of: