Scope Management
Choose the statement which is NOT true about the scope:
Project scope management includes the processes concerned with all the work and only the work required to successfully deliver to the stakeholders' expectations, manage changes and get acceptance of the product in order to complete the project.
Project scope describes work needed to deliver a product or service with the specified features.
Product scope describes the features and functions that characterize a product or service.
The project team has to go above and beyond the defined scope and impress customers by implementing extra features that will be of great benefit to the customers.