Scope Management
A technical project in the company that hired you as the project manager has been assigned to you. The project product is the complete installation of a new operating system on 200 workstations. In your project cost and time estimates you have informed the customer that the estimates provided will be accurate if the workstations meet the hardware requirements of the new operating system. This is an example of: