PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Scope Management
The project is almost complete. The project has a schedule variance of 500 and a cost variance of -700. Almost all of the quality control inspections have been completed and all have met the quality requirements. All items in the issue log have been resolved. Most of the resources have been released. The sponsor is about to call a meeting to obtain product validation when the customer informs the project manager that they want to make a major change to the scope. What should the project manager do?