PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
The project manager is overseeing the project to convert a two-lane highway into a multi-lane highway. The architectural design and site surveys are completed. The project manager is now waiting for the clearance and permit from the city to start the construction. How do you call this type of dependency?