PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
While reviewing one of the activities of a team member, the project manager notices that the activity has an early start of day 4, an early finish of day 11, a late start of day 14 and a late finish of day 21. The team member says that he needs 3 additional days to complete the activity. Which of the following statements is TRUE?