PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
The project manager and his team are in conflict on the amount of time allotted to complete certain activities. Some of the team members want to bloat the time associated with activities to make sure they will have enough time to complete their tasks in case something goes wrong. The law of economics that these tasks may suffer from is which one of the following?