PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
The project manager and the project team are about to enter the activity duration estimating process. Which of the following will not be helpful in your meeting?