Schedule Management
The project manager is working with his customer stakeholder. The stakeholder has asked that the project manager finds a way to reduce the overall project duration for her company. She has promised a bonus to the company if the project is finished ahead of schedule. Which duration compression technique could be utilized on activities that are effort-driven?