PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
You are managing a project on a new drone accessory. The sponsor has made a long list of requirements. The product must adhere to high quality standards and be ready in time for image show which will take place in half a year. The sponsor promised to provide all necessary resources to complete the project within these constraints. Your project management plan results in a project schedule that is too long. If the project network diagram cannot change but you have extra personnel resources available, the best thing to do would be: