PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Schedule Management
John has about 15 years of project management experience. He just started working in a new company and was already given a medium-sized project. The company has many projects to complete, that's why John has to finish the project as soon as possible. He will be given another project as soon as he has this one baselined. He has to report on the longest time the project will take. The best project management tool to use to determine this is: