Schedule Management
You are managing a project to develop a marketing platform for a social network. Users must be able to sell their personal items like clothes or electronics online without any fees. The hardest part of the project is the integration with already existing network, which was created many years ago with the technologies that are a little outdated now. Several stakeholders want to learn what scheduling software will be used on the project. They also require information regarding formats and frequency of project reporting and types of reports required on the project relating to schedule. This information can be found in: