You are managing a residential construction project. There is a chance that in a while all work will need to stop due to the COVID-19 infection in the neighbouring countries. So far, there are no cases of infection in your country but the management is closely following all the news and updates. This morning, the senior management has requested that you shorten the project schedule by three months by any means. You are planning to approve unlimited overtime for the team and find additional resources despite the fact that it will probably add cost to the project and create potential conflicts. Which technique are you using?