The project manager has been assigned to the project to build an animal rescue center. The survey showed that the selected location is prone to floods. The project manager informed her management about it but was told that for some reasons it would be impossible to change the location. To deal with this issue, the project manager chose a flood resistant foundation for the center. This is an example of which of the following?