PMP Exam Simulator

alarm icon
3h 50m 0s
info iconPMP exam lasts 230min and has 180 questions
info iconUse acceleration to have extra 30m in reserve on exam

lock iconRisk Management

You are managing a project to develop a new payroll system for your company. You decide to survey the experts within your organization on any foreseeable risks with structure, design and intent of the new software with an anonymous form. You later send out subsequent anonymous surveys to a group of experts with the collected information. This is an example of which of the following?