PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Risk Management
You are the project manager of a major project of your organization. You are working with your team and the project stakeholders to identify the risks within the project. Some of the risks have not yet happened and some of the risks are already causing problems. You tell the project team that all risks must be documented in the risk register, but they are not familiar with this document. How would you describe the risk register?