Risk Management
You, the project manager, and the manufacturer have agreed to substitute the type of OSB boards used in the product to a slightly thicker grade should there be more than a 3 percent error in production. The thicker OSB boards will cost more and require that the production slow down, but the errors should diminish. This is an example of: