PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Risk Management
Elizabeth is a project manager and she is working on a very important for the company project. During the Identify Risks process, she and stakeholders identified risks using different methods and created a long list of those risks. Also, Elizabeth made sure all the risks were understood and that triggers had been identified. During the Plan Risk Responses process, she determined ways to mitigate the risks identified by the stakeholders. In this scenario, what has Elizabeth done wrong?