Risk Management
Jacob is a project manager for the construction of a major manufacturing plant. His team consists of members from 10 different countries that work in their own time zones. During the project planning, the team is struggling to come up with an effective way to mitigate or insure against a risk. This work cannot be outsourced or deleted. What is the best solution?